NEW ORLEANS (AP) — A lawyer for the cement contractor on the Deepwater Horizon drilling project says the company has found cement samples possibly associated with BP’s Macondo well that weren’t turned over to the Justice Department for testing.

Halliburton lawyer Donald Godwin told U.S. District Judge Carl Barbier on Thursday that the company believes the material found this week at its lab in Lafayette, La., has no bearing on the ongoing trial over the 2010 oil spill in the Gulf of Mexico.

But a plaintiffs’ attorney countered that the samples are cement a Halliburton employee used for testing of the well before a blowout triggered a deadly explosion.

In an email to the court late Wednesday, Godwin says Halliburton is investigating whether the material should have been turned over in response to subpoenas.

Comments
(0)
Comments-icon Post a Comment
No Comments Yet
*We welcome your comments on the stories and issues of the day and seek to provide a forum for the community to voice opinions. All comments are subject to moderator approval before being made visible on the website but are not edited. The use of profanity, obscene and vulgar language, hate speech, and racial slurs is strictly prohibited. Advertisements, promotions, spam, and links to outside websites will also be rejected. Please read our terms of service for full guides