Credit agencies eyeing Plant Vogtle cost overruns
by Ray Henry, Associated Press
April 10, 2013 03:00 PM | 599 views | 0 0 comments | 5 5 recommendations | email to a friend | print
ATLANTA (AP) — As the cost of building a new nuclear plant in Georgia rises, credit rating agencies are taking critical notice.

Four power utilities — Georgia Power, the Municipal Electric Authority of Georgia, Oglethorpe Power Corp. and the City of Dalton — are building a first-of-its-kind nuclear plant about 30 miles southeast of Augusta. That project was originally expected to cost roughly $14 billion, but it has fallen behind schedule by more than a year and is expected to exceed its budget.

The effort is managed by Southern Co. subsidiary Georgia Power, a large utility with a 46 percent stake in the new plant. In late February, Georgia Power told state regulators that its costs were expected to grow by roughly $737 million to about $6.85 billion. Other utilities have reported similar increases in spending roughly equivalent to their share in the project.

Few analysts are worried about the financial implications for Georgia Power, which has a big balance sheet. So far, elected utility regulators that oversee the monopoly have allowed it to pass along its costs to nearly 2.4 million customers.

Other partners are facing more scrutiny. Last week, Fitch Ratings gave a negative outlook to bonds issued by Oglethorpe Power Corp., which supplies electricity to 1.8 million customers, and owns a 30 percent stake in the two new reactors being built at Plant Vogtle. The company’s share of project costs has risen by $300 million to $4.5 billion, according to financial filings.

Fitch did not change the company’s mid-level credit rating, a ranking that shows analysts think there is low risk that Oglethorpe will fail to repay its lenders. But the negative outlook “reflects Fitch’s concern that further delays and higher costs related to the Vogtle nuclear expansion project could weaken the cooperative’s operating and financial profile beyond original expectations,” the Fitch report said.

Besides increased construction costs and delays, Fitch said questions over the company’s continued access to low-cost loans and an ongoing legal dispute with the plant’s designers and builders over an additional $900 million in unanticipated costs contributed toward the negative outlook. The plant owners have denied responsibility for those costs.

Those concerns were partly offset by Oglethorpe’s decision to partner with Georgia Power, a utility with experience building nuclear plants. Fitch said contracts also help minimize Oglethorpe’s exposure to extra construction costs. Cheaper interest rates and low natural gas prices will moderate increases in electricity costs caused by the nuclear project.

Alan Spen, a senior director for Fitch’s public power group, said Oglethorpe had a contingency budget for the project and has benefited from low interest rates, which helped keep costs down.

“They’ve probably used up a certain amount of that flexibility,” Spen said. “And now with the delays and the litigation and other factors ... I think if things can stabilize and go as expected, that probably would be good for the rating and project. If it continues to cost more and we see more delays, it would have to then get reflected in the rating.”

Oglethorpe, which sells wholesale electricity to smaller power provides, said it believes the nuclear plant will prove cost-effective in the long-run. The company told investors in March that it has more than enough cash to meet its obligations. Regulators do not set its rates, meaning elected officials cannot balk at passing its costs onto customers.

“A construction project of this magnitude can result in some near-term pressure on financial metrics,” Oglethorpe spokesman Greg Jones said in a statement.

Separately, Moody’s Investors Service has not changed its scoring for the power companies building the new reactors at Plant Vogtle. But it released a report in March noting that negative financial pressures were increasing for three bonds issued by the Municipal Electric Authority of Georgia, which owns a 23 percent stake in the new plant.

“Construction delays are a leading indicator of rising costs,” the report said. “We think that further delays and new cost over-runs are likely, and there is a finite level that will be tolerated by ratepayers which could lead to a rating downgrade.”

MEAG officials did not return messages seeking comment.

Moody’s noted that the owners recently poured the first concrete at the plant, a construction milestone. MEAG has strong cash reserves and could finance additional project costs without any legal barriers. To spread its risk, MEAG already has contracts to sell power from the reactors to multiple communities. That helps protect against the possibility that the company’s normal customer base could not use — and therefore pay — for all the new electricity when the plant comes online, said Dan Aschenbach, a senior vice president at Moody’s and its lead analyst on MEAG. Aschenbach said those contracts appear relatively firm.

“If this gets too high of a burden, when they start phasing in rates later on, it could be, in a worst-case situation, there could be efforts to look at the contract,” he said.

Comments
(0)
Comments-icon Post a Comment
No Comments Yet
*We welcome your comments on the stories and issues of the day and seek to provide a forum for the community to voice opinions. All comments are subject to moderator approval before being made visible on the website but are not edited. The use of profanity, obscene and vulgar language, hate speech, and racial slurs is strictly prohibited. Advertisements, promotions, spam, and links to outside websites will also be rejected. Please read our terms of service for full guides