Georgians tout passenger trains to Atlanta
by Mike Owen, The Columbus Ledger-Enquirer
August 15, 2014 08:00 AM | 1156 views | 0 0 comments | 0 0 recommendations | email to a friend | print

COLUMBUS, Ga. (AP) — Columbus Mayor Teresa Tomlinson and State Rep. Calvin Smyre were part of a delegation that met this week with high-ranking federal officials on the subject of the proposed rail line between Columbus and Atlanta, Tomlinson said.

Smyre is co-chairman of the Mayor's Commission on Passenger Rail along with attorney Edward Hudson, who also traveled to Washington, D.C., with the Georgia delegation.

The delegation met with Joseph C. Szabo, the administrator of the Federal Railroad Administration, Secretary of Transportation Anthony Foxx and members of Vice President Joe Biden's senior staff to pitch the proposed line between Georgia's two largest cities.

"High-speed rail lines are going to be built," Tomlinson said. "We want to make sure that Columbus is near the front of the line when they are."

In 2012, Tomlinson appointed a 30-person passenger rail commission to study the proposal, and then commissioned a $360,000 feasibility study, which was funded with a Georgia Department of Transportation grant and local private donations.

The consulting firm the conducted the study, HNTB Corp., developed three possible rail proposals, which it estimated would cost from $1.3 to $3.9 billion dollars over a 20-year span.

That study concluded that the most expensive of the proposals, a rail line following the rights of way of Interstates 85 and 185 at speeds from 150-220 mph, could be profitable in its first year of operation. The positive findings of that study were presented in Washington this week and are one reason Columbus is on the map when it comes to passenger rail, Tomlinson said.

"Columbus is getting this attention now because our project is doable," Tomlinson said. "The rail line will run only 90 miles, which is bite-sized compared to a lot of other proposed projects around the country. We also have a known history of successful public-private partnerships in Columbus."

The next step is to seek a grant to perform the Phase 1 National Environmental Policy Act (NEPA) study, which is necessary before the project can move forward. After that and another NEPA study are performed, the project will enter preliminary design, then final design stages before any necessary right of way acquisition can be done, according to HNTB's report.

That could take as long as 18 years, the report states, and then construction could take another two years.

Tomlinson has said the project could produce as many as 11,000 jobs, the equivalent of four KIA plants, but as important as that would be connecting Columbus to the state's largest economic engine.

"This isn't just about going to Braves games," Tomlinson said when the study was released. "It's literally about making Atlanta a bedroom community of Columbus and Columbus a bedroom community of Atlanta."

___

Information from: Columbus Ledger-Enquirer, http://ledger-enquirer.com



Copyright 2014 The Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.



Comments
(0)
Comments-icon Post a Comment
No Comments Yet
*We welcome your comments on the stories and issues of the day and seek to provide a forum for the community to voice opinions. All comments are subject to moderator approval before being made visible on the website but are not edited. The use of profanity, obscene and vulgar language, hate speech, and racial slurs is strictly prohibited. Advertisements, promotions, spam, and links to outside websites will also be rejected. Please read our terms of service for full guides